News

Turner Street Intersection Update - May 5, 2026

5 May 2026

Wondering how the Turner Street Intersection Improvements are coming along? Here is a snapshot of the work being done and what's happing next.

Current and Completed Work

The project is moving along. Here's what's been happening so far:

  • Phase 1 (North side) of construction is on track for completion in late May
  • Stormwater infrastructure work is nearing completion and regrading of the road is underway
  • Hydro pole relocation is complete

What's Next?

As we get closer to completing Phase 1, here's what will be happening next:

  • Telecom relocation is complete
  • Preparation of North side road base
  • Installation of curbs

Following the completion of Phase 1, a detour adjustment will be made to begin work on the Phase 2 (South side). An update will be provided at that time.