Wondering what's happening on High Street? Here is a snapshot of the work being done and what's happing next.


Grosvenor Street to Albert Street

South Side (Current construction area)

Storm sewer installation is now complete in this section.

The next phase includes:

  • Placement of road base
  • Installation of concrete curbs
  • Once curbs are in place, sidewalk removal and new concrete pouring will begin.

To reduce the impact to pedestrian access, the sidewalk will be completed in small sections and efforts will be made to work around business hours.

North Side

Work in this section will begin after completion of all south side infrastructure (storm sewers, curbs, and road base from Grosvenor to Victoria).

Albert Street to Victoria Street

South Side (Current construction area)

Roadwork is underway, including:

  • Installation of storm sewers
  • Placement of underground structures

Work is progressing toward the Victoria Street intersection, including:

  • Continued storm sewer installation
  • Asphalt removal

After curb installation, sidewalk replacement will begin in small sections similar to the previous block to reduce the impact to pedestrian access.

North Side

Public parking remains available in this section.


Further updates will be provided as work progresses.